GAS STATIONS AND PLANTS
Plaquemines 2 – Megamodule
Year 2024
Place: Luisiana, USA (place of final destination)
End Customer: Venture Global LNG
Client: Baker Hughes
Contractor: RAM
The Plaquemines project (Part of Venture Global LNG) consists in the construction of 18 Mega Modules each consisting of 2 modules for the treatment of LNG to be installed in the production site in Luisiana (USA). The modules construction is carried out in the Baker Hughes Yard in Avenza (Carrara MS).
The scope of work of ETI SpA consists in the erection of piping, equipment, valves and supports of Nr. 3 modules. 1 Module almost finished, 1 module currently in construction, 1 module will follow the delivery of first one.
Duration 18 Months (Feb 2024/Aug 2025)
Total weight for each module:
Piping weight: 182.000 kg (stainless steel mainly and carbon steel)
Total 3 modules 546.000 kg
Piping range diameter: ½” up to 42 “
Supports weight: 9.000 kg / total 27.000 kg
Valves: 39.000 kg / total 117.000 kg
Equipment: 340.000 kg / Total 1.020.000 kg
Welding inches: 4.500 “ / Total inches: 13.500 “
The current progress welded inches is around 5.600 “ (from March 2024).
Peak workload: 60 resources
Indirect resources: Site Engineer, Quality Engineer, Construction and Site Manager, HSE, etc.
SCS & VA PROJECT COMPRESSOR STATION GRAFENDORF
Year: 2024
Location : Grafendorf - Austria
Role: Mechanical Main Contractor
Main Contractor : ETI S.p.A.
Client :Trans Austrian Gasleitung GmbH
Activities Performed by ETI S.p.A. :
- Valves and Actuators substitution during plant shut down
- New by-passes installation
- Manual Welding Carbon Steel for Stations Prefabrication and Erection
- Non -Destructive-Test
- Flange management ( Installation and Torquing)
- Hydrotest and dewatering
- Coating and Painting
- Scaffolding installation
- Plant, Decompression , Purging and Recompression with Nitrogen
SCS & VA PROJECT COMPRESSOR STATION BAUMGARTEN
Year: 2023
Location : Baumgarten an der March-Austria
Main Contractor : ETI S.p.A.
Client :Trans Austrian Gasleitung GmbH
Activities Performed by ETI S.p.A. :
- Valves and Actuators substitution during plant shut down
- New by-passes installation
- Manual Welding Carbon Steel for Stations Prefabrication and Erection
- Non -Destructive-Test
- Flange management ( Installation and Torquing)
- Hydrotest and dewatering
- Coating and Painting
- Scaffolding installation
- Plant, Decompression , Purging and Recompression with Nitrogen
ARGE LNG BRUNSBUTTEL PROJECT -PHASE 1 -DN600
Year: 2022
Location : Brunsbüttel-Germany
Role: Mechanical Subcontractor
Main Contractor : PPS Pipeline Systems GmbH
Client : Gasunie Deutschland Transport services GmbH
Activities Performed by ETI S.p.A. :
- Manual Welding Carbon Steel for Stations Prefabrication and Erection
- Flange management
- Hydrotest and dewatering
- Manual Welding of pipeline connection welds DN 600
RAG PROJECT-DN700
Year: 2022
Location : Überackern- Austria
Role: Mechanical Subcontractor
Main Contractor : PPS Pipeline Systems GmbH
Client: R.A.G. Austria
Activities Performed by ETI S.p.A. :
- Manual Welding Carbon Steel for Line Valve Stations Prefabrication and Erection
- Flange management
- Stringing Activity on Pipeline DN 700
- Manual Welding of pipeline welds (mainline and connections) DN 700
- Tie-ins with existing plant
BALTIC PIPE PROJECT- GOLENIOW COMPRESSOR STATION -DN1000
Year: 2021
Location: Goleniow- Poland
Role: Mechanical Subcontractor
Main Contractor: Max Streicher S.p.A.
Client: Gaz-System
Activities Performed by ETI S.p.A.:
- Welding piping prefabrication and erection Carbon Steel
- Welding piping prefabrication and erection Stainless Steel including Pickling
- Tie-ins with existing plant
- Coating activities
- Paiting activities
- Pressure test, blowing and drying activities
- Piping Insulation
- Pre commissioning activities
CAPACITY4 GAS EXTENSION PROJECT- DN1400
Year: 2020
Location: Plzen- Czech Republic
Role: Mechanical Subcontractor
Main Contractor: Sicim S.p.A.
Client: Net4Gas s.r.o.
Activities Performed by ETI S.p.A.:
- Manual Welding for LVS and Pig-Trap Station Construction
( prefabrication and erection) DN 1400
- Underground Coating activities
- Aboveground Painting activities
- Assistance to Hydrotest
- Flange Management
ARGE ZEELINK LOS 4 plus PROJECT- DN1000
Year: 2019
Location: Duisburg- Germany
Role: Mechanical Subcontractor
Main Contractor: PPS Pipeline Systems GmbH
Client: O.G.E
Activities Performed by ETI S.p.A.:
- Manual Welding for BVS and Pig-Trap Station Construction
( prefabrication and erection) DN 1000
- Underground Coating activities
- Aboveground Painting activities
- Assistance to Hydrotest
- Flange Management
EUGAL PROJECT- LOSE 9-10-11 -DN1400
Year: 2018
Location: Großenhain-Germany
Role: Mechanical Subcontractor
Main Contractor: Bonatti S.p.A.
Client : GASCADE Gastransport GmbH
Activities Performed by ETI S.p.A.:
- Manual Welding for BVS and Pig-Trap Station Construction
( prefabrication and erection) DN 1400
- Underground Coating activities
- Aboveground Painting activities
- Assistance to Hydrotest
- Flange Management
Perché scegliere ETI S.p.A.
-
Qualità
esperienza ed ottima reputazione
-
Puntualità
rispetto delle tempistiche
-
Sicurezza
attestati e certificati internazionali
-
Leadership
operiamo in Italia e nel Mondo
il tuo partner di fiducia Eurotecnoimpianti S.r.l.
diventa ETI S.p.A.
Forniamo servizi su tutte le principali attività nel settore Oil&Gas. Svolgiamo attività che coinvolgono tutta la catena di trasporto e stoccaggio di idrocarburi, dalla costruzione di impianti e condotte, alla loro manutenzione e riparazione.-
Address
Via Cesare Battisti, 31, 72025 San Donaci (BR)
Via Strada Del Petraro, snc, 73010 Guagnano (LE)
Via Giulio Pastore, 151, 47522 Cesena (FC) -
Contacts
Phone: +39 0547 072547
Fax: +39 0547 072546
Email: info@etispa.com